PHYSICAL SCIENCES BUILDING
PHASE II FACTS:
Notice to proceed with construction: May 8, 2009
Substantial Completion Date: Aug. 11, 2010
Final Completion Date: September 10, 2010
Total Budget: $30,274,000
Phase II Size: Approx. 38,700 sq. ft. net assignable space.
Total Size: [Phase 1 + Phase 2] Approx. 66,700 sq. ft. of assigned space [i.e., not including corridors, closets, bathrooms, etc.]
Measured Spaces Include:
- Faculty and Post Doc Offices
- Graduate Student shared offices
- Chemistry and Physics Home Department Offices, including:
- staff offices
- reception areas
- break rooms
- copy and mail business areas
- Large Shared Conference Room on first floor opening to 2-story Atrium
- Other small conference, seminar and discussion spaces
- Individual and Shared general chemistry and physics research laboratories
- Specialized Research Laboratory spaces including
- Shared NMR/EPR Lab
- Shared Cold Room
- Shared Surface Science lab
- Synthetic Chemistry Lab
- AutoClave lab
- Laser Lab
- Computer Cluster lab
- Planetary Science labs/workrooms
- Clean Room